The NYTimes reports that the GAO released a report showing that in calling for the cancellation of FutureGen (the integrated IGCC, CCS, hydrogren demonstration plant), they compared the original estimated cost in constant dollars to a new estimate that was in current dollars. Now to be fair, just last week I screwed up deflating some data. To be reasonable, I was not determining the fate of a billion-dollar project:
According to the report, in calculating the costs of the project, the Energy Department mistakenly compared two numbers that should not have been used together. One cost estimate was made in so-called constant dollars, reflecting the purchasing power of a dollar in 2005, and the other in dollars as they would have been spent over the following few years, worth less each year because of inflation.
The Bush administration said the projected cost had nearly doubled, to $1.8 billion from $950 million; the auditors said it had gone to $1.3 billion, up 39 percent.
Ummm…this is not new. I went to a hearing of the Energy and Water Appropriations Subcommittee back on May 8, 2008. I never got around to writing a post, but looking through my old notes from that hearing, I can tell you with certainty that both Sens. Durbin and Dorgan directly asserted that the main source of cost overruns was due to inflation accounting. Then-Secretary of Energy Bodman denied this, and kept claiming he didn’t know what the source of the overruns were, but that the other folks at DOE surely had the answer.
As it turned out, those in attendance only had to wait half an hour or so for the answer. And it came from FutureGen chairman Paul Thompson. To paraphrase, he said that the project cost was indeed $1.8 million — in nominal dollars. That hearing was zeroing in on an answer. Too bad Bodman left the hearing before Thompson gave his testimony.
Indeed FutureGen’s costs rose — as delays continued, it cost money to hold up construction, interest accrued, and so on. But 50 percent of the overrun claimed by the DOE was due to a clerical error. Competence and honesty points abound for the Bush administration.
